Under a developer contract (Bauträgervertrag), the buyer acquires a plot of land or an apartment and at the same time has it built. The contract must be notarised. It combines sales law and contract-for-work law (sections 650u, 650v BGB) with the requirements of the German Real Estate Agents and Developers Ordinance (MaBV).
Payments under the MaBV
The developer may only accept payments according to construction progress. Section 3 MaBV sets out which shares may fall due after which construction stages; the partial amounts may be combined into a maximum of seven instalments. One prerequisite is a priority notice of conveyance in favour of the buyer. Alternatively, a security under section 7 MaBV is possible.
Acceptance of the common property
Clauses under which the common property is accepted by an expert or property manager appointed by the developer are often invalid. The consequence: acceptance has not taken place, defect rights continue to exist, and the limitation period does not begin. Since 2020, the community of apartment owners decides on pursuing defects in the common property.
Review before the notary appointment
- Building specification, drawings, special requests
- Completion date and consequences of delay
- Payment plan and securities
- Acceptance provisions and powers of attorney
- Provisions on parking spaces, special rights of use and the declaration of division
Case studies
Invalid acceptance by the first property manager
Situation: Six years after moving in, the owners of a 24-unit complex discovered damp damage in the underground car park.
Approach: We proved that acceptance by the property manager appointed by the developer was invalid.
Outcome: The defect claims were not time-barred; the developer repaired the waterproofing.
Instalment demanded too early
Situation: A developer demanded the instalment for the shell, although the roof had not yet been covered.
Approach: We had the construction progress documented and withheld payment.
Outcome: The instalment was only paid once the construction stage had been reached.
Developer insolvency
Situation: A developer became insolvent after completing the shell.
Approach: We secured the rights under the priority notice and the contract and negotiated with the insolvency administrator.
Outcome: The buyers were able to have the property completed by another company.
The examples are anonymised and simplified. They illustrate typical situations; every case is different, and no particular outcome can be promised.
Frequently asked questions
Can I have the developer contract reviewed before notarisation?
Yes. The notary must generally provide consumers with the draft two weeks before notarisation. You should use this time for a review.
Do I have to pay the last instalment if there are defects?
Where there are defects, you have a right to withhold performance, usually in the amount of twice the cost of remedying the defects.
Last updated: · horak Rechtsanwälte, Hanover. General information under German law, not legal advice in an individual case.