Project management agreement

Project managers take on tasks of the client. We define services, authority and liability so that there are no gaps.

Project managers support clients with organisation, costs, scheduling and quality. Unlike architects, there is no binding fee scale for them. The scope of services and liability arise solely from the contract.

Scope of services

In practice, reference is often made to the scope of services set out in the AHO series (volume 9). It divides the services into project stages and fields of action such as organisation, quality, costs, scheduling and contracts. If project leadership with decision-making powers is transferred, this must be agreed separately.

Whether a project management agreement is a contract for services or a contract for work depends on the services undertaken. If the project manager owes specific results, such as a cost determination or a schedule, the rules on contracts for work apply to that extent. This determines acceptance, defect rights and limitation periods.

Key provisions

  • Demarcation from the services of architects and specialist designers
  • Powers of attorney and decision-making authority
  • Responsibility for costs and deadlines
  • Fees, additional services where construction time is extended
  • Limitation of liability and insurance

Case studies

Duplicate commissioning avoided

Situation: A municipal client had commissioned cost control both from the architect and from the project manager.

Approach: We compared the scopes of services and adapted the contracts.

Outcome: Duplicate fees were eliminated, and responsibility was clearly allocated.

Fees where construction time is extended

Situation: After an eleven-month extension of construction time, a project manager demanded additional fees.

Approach: We analysed the contract provision on the term and set out the additional effort in a comprehensible way.

Outcome: The client paid an additional time-related fee.

Faulty scheduling

Situation: An investor claimed delay damages from the project manager.

Approach: We examined which deadlines were owed as a result under a contract for work and where third parties were responsible.

Outcome: The claims were limited to the share that could be proven to have been caused.

The examples are anonymised and simplified. They illustrate typical situations; every case is different, and no particular outcome can be promised.

Frequently asked questions

Does the HOAI apply to project management?

No. The HOAI does not regulate project management. Fees are freely agreed.

May a project manager commission change orders?

Only if they have been granted a corresponding power of attorney. Without it, their declaration generally does not bind the client.

Last updated: · horak Rechtsanwälte, Hanover. General information under German law, not legal advice in an individual case.