Whether a project is approved is often decided while the building application is being prepared. We support clients, project developers and designers through the procedure under the Lower Saxony Building Code (NBauO) and, if necessary, enforce permits before the administrative courts.
Preliminary enquiry and building application
A preliminary building enquiry makes it possible to clarify individual questions in advance with binding effect, such as admissibility under planning law according to sections 30 to 35 BauGB. The outline decision binds the authority for the later permit procedure. For the building application, complete documents are essential; missing evidence delays the procedure considerably.
Refusal: action instead of objection
In Lower Saxony, the objection procedure against building law decisions has largely been abolished. An action for issue of a permit must therefore generally be brought directly before the administrative court against the refusal of a building application, within one month of notification (section 74 VwGO). The information on legal remedies in the decision states the correct route; we always check it.
Inactive authority
If the authority does not decide within a reasonable period without sufficient reason, an action for failure to act is admissible after three months (section 75 VwGO). Often, announcing it is enough to get a stalled procedure moving.
Our services
- Planning law review before land purchase and building application
- Preliminary enquiries, deviations, exceptions and exemptions
- Negotiations with the building control authority and the municipality
- Actions for issue of a permit and for failure to act, leave to appeal before the Higher Administrative Court of Lüneburg
Case studies
Exemption for a loft conversion obtained
Situation: The building control authority refused a loft conversion because the dormers exceeded the requirements of the development plan.
Approach: We applied for an exemption and supported it with comparable precedents in the neighbourhood.
Outcome: The authority granted the exemption; no action was necessary.
Action for a permit for a commercial hall
Situation: A hall in an outlying area was refused as not privileged, although it served an agricultural business.
Approach: We filed an action in time and proved the operational connection with an expert opinion.
Outcome: The administrative court ordered the district to grant the permit.
Standstill ended by an action for failure to act
Situation: A building application for an apartment building had been lying unprocessed at the authority for five months.
Approach: We announced an action for failure to act and documented that the application was complete.
Outcome: The building permit was granted a few weeks later.
The examples are anonymised and simplified. They illustrate typical situations; every case is different, and no particular outcome can be promised.
Frequently asked questions
Do I have to file an objection in Lower Saxony?
In most building law cases, no. The information on legal remedies in the decision is decisive. The deadline for filing an action is one month.
How long is a building permit valid?
Under the NBauO, it lapses if construction is not started within three years or is interrupted for three years. The period can be extended on application.