The construction contract is the foundation of every construction project. It determines what is owed, what it costs, when it must be finished – and who bears which risks. Mistakes in drafting often only show months later, but then with considerable financial consequences.
Legal basis of private construction law
Private construction law governs the legal relationships between the parties involved in construction. Its basis is the law on contracts for work in the German Civil Code (BGB) (sections 631 et seq.), which since 2018 has been supplemented by specific provisions for the construction contract (sections 650a–650h BGB), the consumer construction contract (sections 650i–650o BGB), the architect and engineer agreement (sections 650p–650t BGB) and the developer contract (sections 650u, 650v BGB).
Key innovations of the statutory construction contract law are the client’s right to order changes (section 650b BGB) with a procedure for agreeing on changes, price adjustment based on the costs actually required (section 650c BGB), the joint condition survey where acceptance is refused (section 650g BGB) and the written form requirement for termination (section 650h BGB).
BGB or VOB/B?
The German Construction Contract Procedures, Part B (VOB/B), are not a statute but a set of standard terms that must be agreed in the contract. Public clients are obliged to use them; in the private sector they are widespread. Key differences:
| Topic | BGB construction contract | VOB/B contract |
|---|---|---|
| Changes to the works | Right to order changes with negotiation phase (section 650b BGB) | Right to order changes under § 1(3), (4) VOB/B |
| Payment for change orders | Costs actually required plus mark-ups (section 650c BGB) | Extrapolation of the original pricing (§ 2(5), (6) VOB/B) |
| Acceptance | Formal, implied or deemed (section 640 BGB) | Additionally, deemed acceptance under § 12(5) VOB/B |
| Limitation of defect claims | 5 years for buildings | 4 years unless otherwise agreed |
| Final invoice | Verifiable final invoice (section 650g(4) BGB) | Detailed rules on invoicing and final payment (§§ 14, 16 VOB/B) |
If the VOB/B is used with consumers or is not agreed „as a whole“, its clauses are subject to review as standard business terms. Many provisions do not withstand this review.
Contract models
- Separate trade contracts: the client commissions each trade separately and bears the coordination risk.
- General contractor: one company takes on all construction work, often at a fixed lump-sum price.
- Turnkey contractor (Generalübernehmer / Totalunternehmer): additionally takes on the design.
- Subcontracts: passing on work while „flowing down“ the obligations from the main contract.
- Collaborative models: partnering, alliance contracts and integrated project delivery (IPA).
International construction contracts
Cross-border projects frequently use the FIDIC contract forms. They allocate roles and risks differently from German law and provide for strict deadlines for notifying claims. We advise on drafting, adapting them to the applicable law and claim management.
Our services in construction contract law
- Drafting construction contracts, general terms and conditions and negotiation records
- Reviewing draft contracts with a risk overview for clients or contractors
- Legal advice during construction: correspondence, notices of concerns and disruption, change orders
- Change order and claim management
- Termination and final accounts of terminated construction contracts
- Representation in conciliation, arbitration and construction litigation
Case studies
Oral construction contract made provable
Situation: A roofer had carried out additional work on a client’s verbal instruction; the client denied ever placing the order.
Approach: We combined messages, photos and statements from employees into a complete account.
Outcome: The client acknowledged the order and paid the invoice after a small reduction.
Termination for good cause properly prepared
Situation: A client wanted to terminate a contractor who had not appeared on site for weeks.
Approach: We first set a deadline with a warning of termination and had the progress of the work documented.
Outcome: The termination was effective; the additional costs of the replacement contractor were set off against the outstanding contract price.
Draft contract for an office building
Situation: A medium-sized investor wanted to commission a general contractor to build an office building.
Approach: We drafted the contract with a clear specification, schedule, contractual penalty and securities.
Outcome: The project was completed without litigation; change orders were settled under the agreed procedure.
The examples are anonymised and simplified. They illustrate typical situations; every case is different, and no particular outcome can be promised.
Frequently asked questions
Does a construction contract have to be in writing?
Generally not – oral construction contracts are also valid. Exceptions exist, for example, for consumer construction contracts (text form) and developer contracts (notarisation). For evidential reasons, however, a written contract with a precise specification is strongly recommended.
What happens if the client changes the works?
Under a BGB construction contract, the parties should first try to agree on the change and the increase or reduction in price. If this fails within 30 days, the client can order the change. Payment is then based on the costs actually required plus reasonable mark-ups, or on a deposited original calculation.
Can I terminate a construction contract early?
The client can terminate a contract for work at any time for convenience, but then generally owes the agreed price less saved expenses. In the case of termination for good cause, this claim does not apply to the work not performed. Termination of a construction contract must be in writing.
Last updated: · horak Rechtsanwälte, Hanover. General information under German law, not legal advice in an individual case.