The developer contract

Under a developer contract (Bauträgervertrag), the developer undertakes to build a house or apartment and at the same time to transfer ownership of the land (section 650u BGB). Contract-for-work law applies to the construction and sales law to the land. The contract must be notarised, including the building specification and drawings.

The developer may only accept payments in accordance with the German Real Estate Agents and Developers Ordinance (MaBV): according to construction progress in no more than seven instalments drawn from the statutory construction stages, and only once certain securities are in place – such as the priority notice of conveyance, the release from encumbrances and the building permit. Alternatively, a guarantee under section 7 MaBV is possible.

Defects and acceptance with developers

  • Separate ownership: each buyer accepts their own apartment and asserts defects themselves.
  • Common property: the façade, roof, underground car park and stairwell concern all owners. The community of apartment owners can take over the assertion of defect rights.
  • Acceptance of common property: clauses under which an expert or property manager appointed by the developer declares acceptance are often invalid – with the result that the limitation period does not begin.
  • Delayed completion: claims for delay damages and loss of use.

Project development

Successful project development starts with a robust legal structure:

  • Securing landPurchase rights, options, conditional purchase agreements, due diligence on contamination, building encumbrances and easements.
  • Planning lawPreliminary building enquiry, project-related development plan, urban development contracts and implementation agreements.
  • Project contractsDesign and general contractor agreements, project management, financing and security concepts.
  • Sales and exploitationDeveloper contracts, declaration of division, forward deals and letting.

Our services

For buyers: reviewing the developer contract and building specification before the notary appointment, checking instalment payments, accompanying acceptance, enforcing defect and delay claims, advising communities of apartment owners.

For developers and project developers: drafting MaBV-compliant contracts and building specifications, structuring projects, contract management with designers and general contractors, defending unjustified defect claims.

Case studies

Buyers obtain a completion date

Situation: A developer repeatedly postponed the handover of condominiums.

Approach: We calculated the buyers‘ delay claims and claimed loss of use.

Outcome: The buyers received compensation, and the apartments were handed over promptly.

Invalid acceptance clause

Situation: A developer had the common property accepted by an expert it had appointed itself.

Approach: On behalf of the community of owners, we challenged the clause as invalid.

Outcome: The defect claims did not become time-barred; the defects were remedied.

Project development in a joint venture

Situation: Two companies wanted to develop a mixed residential and commercial quarter together.

Approach: We structured the partnership agreement, the transfer of land and the developer contracts.

Outcome: The project started with clear responsibilities and exit rules.

The examples are anonymised and simplified. They illustrate typical situations; every case is different, and no particular outcome can be promised.

Frequently asked questions

Should I have the developer contract reviewed before the notary appointment?

Definitely. The notary is obliged to remain neutral and does not advise one side. Unclear building specifications, acceptance clauses, completion dates without sanctions and reservations of the right to make changes are frequently problematic. Consumers must generally receive the draft two weeks before notarisation – use this time.

What can I do if the developer becomes insolvent?

What matters is whether the instalments were paid in compliance with the MaBV and whether a priority notice of conveyance has been registered. If so, the buyer can usually obtain transfer of ownership and have the property completed by third parties. We examine the securities and the options in the insolvency proceedings.

Last updated: · horak Rechtsanwälte, Hanover. General information under German law, not legal advice in an individual case.

Enquiry

Your question about Developers & projects

Briefly describe the facts. We will get back to you with an initial assessment of the approach and costs.

We use your details only to process your enquiry. For details, please see our privacy policy.

Encrypted transmission. An enquiry does not create a client relationship; deadlines cannot be met via this form.