Interim injunctions in construction law

When time is short: we secure claims before facts are created on the ground.

An interim injunction (sections 935, 940 ZPO) secures rights provisionally until the main proceedings have been decided. In construction law, it is particularly important for contractors‘ security rights and for disputes over instructions during construction. Courts often decide within a few days, sometimes without an oral hearing.

Priority notice for the security mortgage

Contractors for a building can demand a security mortgage over the client’s building plot for their claim (section 650e BGB). To secure priority, a priority notice is entered in the land register by interim injunction (section 885 BGB). It is not necessary to show that the claim is at risk. The client and the owner of the land must be the same person.

Disputes over instructions and payment for changes

Since the reform of construction contract law, section 650d BGB has made interim relief easier in disputes over the client’s right to order changes and the adjustment of the price. Once construction has started, urgency does not have to be substantiated. This makes it possible to clarify whether changed work must be carried out or whether interim payments must be made on a change order.

Other applications

  • Prohibiting a call on a guarantee where there is obviously no secured event
  • Handing over drawings and documents indispensable for continuing construction
  • Access to the site, securing evidence
  • Defending against nuisance to neighbours from construction work

Our services

  • Rapid assessment of the claim and the supporting evidence, statutory declarations
  • Filing applications and representation in summary proceedings, protective letters
  • Enforcement, entry in the land register and transition to the main proceedings

Case studies

Priority notice registered within a week

Situation: A shell contractor learned that the client intended to sell the plot after completion while its final invoice was still unpaid.

Approach: We applied for an interim injunction for the registration of a priority notice and arranged enforcement at the land registry.

Outcome: The priority notice was registered; the client paid out of the purchase price.

Interim payment on a change order secured

Situation: A client ordered a changed foundation but refused any additional payment.

Approach: In proceedings under section 650d BGB, we claimed payment of 80 percent of the change order offer as an interim payment.

Outcome: The court largely granted the application, and construction continued without interruption.

Call on a guarantee prevented

Situation: A client wanted to call a performance guarantee even though the work had been accepted and the final account settled.

Approach: We set out to the client and the bank that there was no security agreement covering this and applied for an injunction.

Outcome: The call was prohibited, and the guarantee was later returned.

The examples are anonymised and simplified. They illustrate typical situations; every case is different, and no particular outcome can be promised.

Frequently asked questions

How quickly does the court decide?

In urgent cases within a few days. Anyone who waits too long risks the court denying urgency.

What happens after the interim injunction?

The injunction only provides a provisional arrangement. The opponent can file an objection or demand that an action be brought in the main proceedings.

Last updated: · horak Rechtsanwälte, Hanover. General information under German law, not legal advice in an individual case.