VOB/B construction contract

The VOB/B is the most widely used set of standard terms in German construction. We make sure it is validly agreed and that your rights under it are not lost through missed deadlines.

The German Construction Contract Procedures, Part B (VOB/B), are not a statute but standard business terms that must be incorporated into the contract. They are mandatory for public clients and standard in commercial construction. Anyone working with them needs to know their deadlines and formal requirements.

Valid incorporation

The VOB/B only applies if it has been validly incorporated into the contract. Between businesses, an express reference is usually sufficient. If the VOB/B is agreed „as a whole“ without any changes to its content, it is largely exempt from the statutory review of standard terms in dealings with businesses and public clients (section 310(1) sentence 3 BGB). Even minor deviations in special or additional contract conditions, however, open up every single clause to review. In contracts with consumers, the VOB/B is always subject to full review.

Key provisions at a glance

Provision Content Practical tip
§ 1(3), (4) Client’s right to order changes Document instructions and have them confirmed in writing
§ 2(5), (6) Payment for changed and additional work Give notice of the claim for additional payment before carrying out additional work
§ 4(3) Notice of concerns In writing, specific, and addressed to the client itself
§ 6(1) Notice of disruption Without delay and in writing, otherwise extensions of time and claims may be lost
§ 12 Acceptance, including deemed acceptance A notice of completion triggers a 12-working-day period
§ 13(4) Limitation period for defect claims 4 years for buildings unless otherwise agreed
§ 16(3) Final payment Declare a reservation within 28 days and substantiate it within a further 28 days
§ 17 Security Note the contractor’s right to substitute securities

Typical points of dispute

Most disputes concern change orders, construction time and final accounts. Whether work is „additional“ depends on the contractual scope, which must be determined from the bill of quantities, drawings and preliminaries. Where the construction process is disrupted, it is essential to give notice of disruption promptly and to show its effects on the actual sequence of works. If the parties cannot agree on the amount of payment for changes, the case law of the Federal Court of Justice has put the costs actually required at the centre.

Our services

  • Drafting special and additional contract conditions that work together with the VOB/B
  • Reviewing contracts for invalid deviations and risks
  • Template letters for notices of concerns, disruption and additional costs
  • Reviewing and negotiating change orders, final accounts for terminated contracts
  • Enforcing and defending claims, up to and including construction litigation

Case studies

Reservation after final payment preserved

Situation: A shell construction contractor received a substantially reduced payment on its final invoice, with a reference to the exclusionary effect of final payment.

Approach: We declared the reservation in time and substantiated the disputed items in a verifiable way within the second period.

Outcome: The outstanding claim remained enforceable, and a large part of it was paid after negotiations.

Additional work without prior notice

Situation: A client refused to pay for additional dewatering because the change order had not been announced before the work was carried out.

Approach: We showed that the work was indispensable for the project and that the client was aware of its obligation to pay.

Outcome: The change order was accepted in principle; the parties agreed on the amount.

Invalid clause in additional contract conditions

Situation: A general contractor’s contract conditions postponed acceptance until handover to the developer.

Approach: We identified the clause as a deviation from the VOB/B that does not withstand review.

Outcome: The subcontractor was able to demand acceptance; the warranty period and the due date for payment ran from that point.

The examples are anonymised and simplified. They illustrate typical situations; every case is different, and no particular outcome can be promised.

Frequently asked questions

Does the VOB/B apply automatically to construction contracts?

No. It must be agreed in the contract. Without such an agreement, the statutory construction contract law of the German Civil Code (BGB) applies.

Can the VOB/B be agreed with consumers?

Yes, but its clauses are then fully subject to review as standard business terms. Some provisions, for example on deemed acceptance or limitation periods, may be invalid.

Last updated: · horak Rechtsanwälte, Hanover. General information under German law, not legal advice in an individual case.